{"id":27590,"date":"2026-09-23T04:38:38","date_gmt":"2026-09-23T04:38:38","guid":{"rendered":"https:\/\/koshalsambada.in\/?p=27590"},"modified":"2026-09-23T04:38:38","modified_gmt":"2026-09-23T04:38:38","slug":"builder-delayed-rs-44-36-lakh-flat-possession-by-18-months-and-charged-rs-30000-debris-fee-telangana-rera-orders-him-to-pay-homebuyer-10-7-interest-compensation-for-delay","status":"publish","type":"post","link":"https:\/\/koshalsambada.in\/?p=27590","title":{"rendered":"Builder delayed Rs 44.36 lakh flat possession by 18 months and charged Rs 30,000 debris fee; Telangana RERA orders him to pay homebuyer 10.7% interest compensation for delay"},"content":{"rendered":"<p><br \/>\n<\/p>\n<div>\n<div class=\"e9jwa\">\n<div class=\"vdo_embedd\">\n<div class=\"GfdvZ\">\n<section class=\"_bIDB  clearfix id-r-component leadmedia undefined undefined  E9tg9 \" style=\"top:0px\">\n<div class=\"_bIDB\" data-ua-type=\"1\" onclick=\"stpPgtnAndPrvntDefault(event)\">\n<div class=\"ypVvZ\">\n<div class=\"WGttI\"><img src=\"https:\/\/static.toiimg.com\/thumb\/msid-134416525,imgsize-590931,width-400,height-225,resizemode-4\/flat-possession-delays.jpg\" alt=\"Builder delayed Rs 44.36 lakh flat possession by 18 months and charged Rs 30,000 debris fee; Telangana RERA orders him to pay homebuyer 10.7% interest compensation for delay\" title=\"The builder assured the homebuyer that the flat would be ready for possession by December 26, 2024. (Image for representative purpose only)\" decoding=\"async\" fetchpriority=\"high\"\/><\/div>\n<\/div>\n<\/div>\n<div class=\"Ta7d_ img_cptn\"><span title=\"The builder assured the homebuyer that the flat would be ready for possession by December 26, 2024. (Image for representative purpose only)\">The builder assured the homebuyer that the flat would be ready for possession by December 26, 2024. (Image for representative purpose only)<\/span><\/div>\n<\/section>\n<\/div><\/div>\n<\/div>\n<p>You pay for a flat which the builder promises possession of on an agreed timeline. He delays possession beyond the grace period. What do you do in such a case?<span class=\"id-r-component br\" data-pos=\"1\"\/>Telangana RERA has granted relief to a homebuyer in one such case, ordering the building to pay interest compensation. <!-- -->It found that the builder had delayed handing over the flat by 18 months and had also levied an additional Rs 30,000 as a debris charge.<span class=\"id-r-component br\" data-pos=\"5\"\/>The Telangana RERA authority concluded that the builder had not fulfilled its obligations under the Agreement of Sale and Section 11(4)(a) of the <a href=\"https:\/\/timesofindia.indiatimes.com\/topic\/rera-act\" styleobj=\"[object Object]\" class=\"\" commonstate=\"[object Object]\" frmappuse=\"1\" target=\"_blank\" rel=\"noopener\">RERA Act<\/a>. It also rejected the builder&#8217;s contention that the delay was caused by Covid-19.<span class=\"id-r-component br\" data-pos=\"9\"\/><\/p>\n<p><h2>What the case is about<\/h2>\n<\/p>\n<p>A man decided to purchase a flat after seeing an advertisement and checking information available on the builder&#8217;s website. <!-- -->The flat, which was priced at Rs 44.36 lakh, was allotted to him.<span class=\"id-r-component br\" data-pos=\"15\"\/>An Agreement of Sale was signed. The builder assured the homebuyer that the flat would be ready for possession by December 26, 2024. There was also an extended grace period available up to August 2025.<span class=\"id-r-component br\" data-pos=\"17\"\/>Relying on these commitments, the homebuyer paid Rs 40.32 lakh towards the purchase of the flat. This included amounts that were charged for amenities, parking, EV charging and other allied facilities.<span class=\"id-r-component br\" data-pos=\"20\"\/>The promised possession timelines, however, were repeatedly changed by the builder. The homebuyer said he was not given sufficient clarity about when construction would actually be completed, when the promised amenities would be ready or when the Occupancy Certificate would be obtained.<span class=\"id-r-component br\" data-pos=\"22\"\/>There was also the issue of an additional debris charge of Rs 30,000. The homebuyer said this charge had not been disclosed earlier and did not form part of the agreement.<span class=\"id-r-component br\" data-pos=\"25\"\/>The builder, on the other hand, stated that the project had reached nearly 85% completion. It also said that following discussions with homebuyers, the debris charge had been rationalised to Rs 20,000 per flat.<span class=\"id-r-component br\" data-pos=\"27\"\/>Before the Telangana RERA authority, the homebuyer said the delay had put him under continuing financial pressure. He was having to meet his home loan EMI while simultaneously paying rent. He therefore sought interest compensation from the authority under the provisions of the RERA Act.<span class=\"id-r-component br\" data-pos=\"30\"\/><\/p>\n<p><h2>What the builder said<\/h2>\n<\/p>\n<p>The builder defended the delay by saying that it was making efforts to complete the project within the revised deadline of December 2026. It cited several difficulties that had affected the construction schedule, including a shortage of labour, Covid-19 and legal issues relating to encroachment.<span class=\"id-r-component br\" data-pos=\"33\"\/>He relied on the force majeure clause and cited the Covid-19 pandemic as a reason for the delay in the project. The builder also told Telangana RERA authority about an FTL encroachment issue involving some blocks in the society,<span class=\"id-r-component br\" data-pos=\"35\"\/>According to the builder, these issues had a wider impact on the project. <!-- -->They led to operational setbacks, labour dispersal, panic among customers and the withdrawal of institutional funding.<span class=\"id-r-component br\" data-pos=\"39\"\/>The builder further told the authority that the Telangana High Court subsequently clarified that construction work could proceed in blocks other than Blocks 8 and 9. It also said that the HMDA later confirmed there was no substantial FTL violation, apart from a minor issue that had already been rectified.<span class=\"id-r-component br\" data-pos=\"42\"\/>The builder extended the construction deadline to December 18, 2026. This meant that possession of the flat would be delayed by more than 18 months from the originally committed timeline.<span class=\"id-r-component br\" data-pos=\"44\"\/>On August 25, 2026, the homebuyer secured relief from Telangana RERA. The authority directed the builder to pay interest compensation at the rate of 10.7% for the delay in handing over possession, according to an ET report.<span class=\"id-r-component br\" data-pos=\"46\"\/><\/p>\n<p><h2>Why homebuyer won the case<\/h2>\n<\/p>\n<p>Asha Kiran Sharma, Partner at King Stubb and Kasiva, told ET that the Telangana RERA authority rejected the builder&#8217;s reliance on Covid-19 and its subsequent consequences as an explanation for the delay.<span class=\"id-r-component br\" data-pos=\"50\"\/>Sharma said the authority&#8217;s reasoning centred on the timing of the Agreement of Sale. The agreement had been executed in February 2023, considerably after the pandemic had subsided.<span class=\"id-r-component br\" data-pos=\"52\"\/>Therefore, according to the authority&#8217;s reasoning, the builder had entered into its commitment to deliver possession with knowledge of the circumstances in which the project was being executed.<span class=\"id-r-component br\" data-pos=\"54\"\/>It made it clear that the possession date that has been specified in the Agreement of Sale has to be taken into account.<span class=\"id-r-component br\" data-pos=\"57\"\/>The authority also raised objections to the developer&#8217;s actions on issues beyond the delay in handing over possession.<span class=\"id-r-component br\" data-pos=\"59\"\/>One such issue was the Rs 30,000 &#8220;debris charge&#8221; added to the homebuyer&#8217;s account. Telangana RERA rejected this charge, noting that it was not provided for in the Agreement of Sale and was inconsistent with the developer&#8217;s statutory obligations under the RERA Act.<span class=\"id-r-component br\" data-pos=\"61\"\/>Additionally, the payment record clearly showed that the homebuyer had paid Rs 40.32 lakh towards the total flat cost of Rs 44.36 lakh. <!-- -->These payments had been made without any default. Even after fulfilling his payment obligations, however, he did not receive possession by the committed date of December 26, 2024. The flat remained undelivered even after the expiry of the grace period.<span class=\"id-r-component br\" data-pos=\"65\"\/>The Telangana RERA authority held that these circumstances amounted to a breach of the builder&#8217;s contractual and statutory obligations under Section 18 of the RERA Act.<span class=\"id-r-component br\" data-pos=\"68\"\/>The Telangana RERA authority said: \u201cThe material on record clearly demonstrates a continued pattern of false assurances despite the Respondent\u2019s (builder\u2019s) knowledge of its inability to adhere to the committed timelines, while the project admittedly remains incomplete beyond the stipulated possession date.\u201d<span class=\"id-r-component br\" data-pos=\"70\"\/>The Telangana RERA authority clarified that the homebuyer can seek compensation for mental agony, financial loss and any assured compensation amounts promised by the builder by filing an application in Form &#8216;N&#8217; before the Adjudicating Officer under Section 71 of the RERA Act.<span class=\"id-r-component br\" data-pos=\"73\"\/>The authority also struck down the debris charge imposed by the builder. It found that the charge was not supported by the terms of the Agreement of Sale and was contrary to Sections 11(4)(a), 11(4)(d) and 14 of the RERA Act.<span class=\"id-r-component br\" data-pos=\"75\"\/>Telangana RERA directed that the homebuyer is entitled to interest compensation at the rate of 10.7% per annum.<span class=\"id-r-component br\" data-pos=\"78\"\/>The interest is to be calculated on the amounts already paid by the homebuyer and will apply from June 26, 2025 until the date on which lawful possession of the flat is actually handed over.<span class=\"id-r-component br\" data-pos=\"81\"\/>The authority directed the builder to clear the interest arrears accumulated up to the date of the order within 60 days. If the builder does not make the payment, the interest accruing thereafter will have to be paid every month, on or before the 10th day of the following month, until the homebuyer receives possession of the flat.<\/div>\n<p><br \/>\n<br \/><a href=\"https:\/\/timesofindia.indiatimes.com\/business\/india-business\/builder-delayed-rs-44-36-lakh-flat-possession-by-18-months-and-charged-rs-30000-debris-fee-telangana-rera-orders-him-to-pay-homebuyer-10-7-interest-compensation-for-delay\/articleshow\/134416038.cms\" target=\"_blank\" rel=\"noopener\">Source link <\/a><\/p>\n","protected":false},"excerpt":{"rendered":"<p>The builder assured the homebuyer that the flat would be ready for possession by December 26, 2024. (Image for representative purpose only) You pay for a flat which the builder promises possession of on an agreed timeline. He delays possession beyond the grace period. What do you do in such a case?Telangana RERA has granted [&hellip;]<\/p>\n","protected":false},"author":1,"featured_media":27591,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[31],"tags":[],"class_list":["post-27590","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-31"],"magazineBlocksPostFeaturedMedia":{"thumbnail":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","medium":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","medium_large":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","large":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","1536x1536":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","2048x2048":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","blogsy-small":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","blogsy-small-tall":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","blogsy-small-square":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","blogsy-small-masonry":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","blogsy-medium":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","blogsy-medium-masonry":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","blogsy-large":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg","blogsy-wide":"https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg"},"magazineBlocksPostAuthor":{"name":"admin","avatar":"https:\/\/secure.gravatar.com\/avatar\/8709732a479614e7a8aa24d3eb1b239f30dc6d90c61464ed495001e7a469d856?s=96&d=mm&r=g"},"magazineBlocksPostCommentsNumber":"0","magazineBlocksPostExcerpt":"The builder assured the homebuyer that the flat would be ready for possession by December 26, 2024. (Image for representative purpose only) You pay for a flat which the builder promises possession of on an agreed timeline. He delays possession beyond the grace period. What do you do in such a case?Telangana RERA has granted [&hellip;]","magazineBlocksPostCategories":["\u0b26\u0b47\u0b36 \u0b2c\u0b3f\u0b26\u0b47\u0b36"],"magazineBlocksPostViewCount":1,"magazineBlocksPostReadTime":6,"magazine_blocks_featured_image_url":{"full":["https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg",400,225,false],"medium":["https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg",300,169,false],"thumbnail":["https:\/\/koshalsambada.in\/wp-content\/uploads\/2026\/09\/flat-possession-delays.jpg",150,84,false]},"magazine_blocks_author":{"display_name":"admin","author_link":"https:\/\/koshalsambada.in\/author\/admin"},"magazine_blocks_comment":0,"magazine_blocks_author_image":"https:\/\/secure.gravatar.com\/avatar\/8709732a479614e7a8aa24d3eb1b239f30dc6d90c61464ed495001e7a469d856?s=96&d=mm&r=g","magazine_blocks_category":"<a href=\"#\" class=\"category-link category-link-31\">\u0b26\u0b47\u0b36 \u0b2c\u0b3f\u0b26\u0b47\u0b36<\/a>","_links":{"self":[{"href":"https:\/\/koshalsambada.in\/index.php?rest_route=\/wp\/v2\/posts\/27590","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/koshalsambada.in\/index.php?rest_route=\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/koshalsambada.in\/index.php?rest_route=\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/koshalsambada.in\/index.php?rest_route=\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/koshalsambada.in\/index.php?rest_route=%2Fwp%2Fv2%2Fcomments&post=27590"}],"version-history":[{"count":0,"href":"https:\/\/koshalsambada.in\/index.php?rest_route=\/wp\/v2\/posts\/27590\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/koshalsambada.in\/index.php?rest_route=\/wp\/v2\/media\/27591"}],"wp:attachment":[{"href":"https:\/\/koshalsambada.in\/index.php?rest_route=%2Fwp%2Fv2%2Fmedia&parent=27590"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/koshalsambada.in\/index.php?rest_route=%2Fwp%2Fv2%2Fcategories&post=27590"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/koshalsambada.in\/index.php?rest_route=%2Fwp%2Fv2%2Ftags&post=27590"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}